[et_pb_section fullwidth=”on” specialty=”off” transparent_background=”off” background_color=”#480000″ allow_player_pause=”off” inner_shadow=”off” parallax=”off” parallax_method=”off” background_image=”https://nrw.com.au/wp-content/uploads/2015/04/Screen-Shot-2015-05-11-at-10.23.25-am.png”][et_pb_fullwidth_header admin_label=”Fullwidth Header” title=”LATEST NEWS” background_layout=”dark” text_orientation=”left” /][/et_pb_section][et_pb_section fullwidth=”off” specialty=”off”][et_pb_row][et_pb_column type=”1_4″][et_pb_sidebar admin_label=”Sidebar” orientation=”left” area=”et_pb_widget_area_1″ background_layout=”light” /][/et_pb_column][et_pb_column type=”3_4″][et_pb_text admin_label=”Text” background_layout=”light” text_orientation=”left”]

NRW WINS ERNEST HENRY CONTRACT FOR XSTRATA COPPER
15/11/2012
NRW have been contracted to undertake the construction of the 22.5km Monakoff Haul Road to link the three open-cut E1 pits to the two open-cut Monakoff pits, at the Xstrata Copper owned, Ernest Henry mine.Xstrata Copper owns and operates the open-cut and underground mining and processing operation 38km north of Cloncurry in North-West Queensland.Deemed operations critical, we are required to mobilise and construct the road within a 60 day period. Construction works include clear and grub, topsoil strip and stockpile, cut to fill, and pavement works.

To reduce critical construction time, and to manage the scarce on-site water, NRW has elected to pug the pavement material off-site before carting into the road box for placement, compaction and trimming.

[/et_pb_text][/et_pb_column][/et_pb_row][/et_pb_section]