[et_pb_section fullwidth=”on” specialty=”off” transparent_background=”off” background_color=”#480000″ allow_player_pause=”off” inner_shadow=”off” parallax=”off” parallax_method=”off” background_image=”https://nrw.com.au/wp-content/uploads/2015/04/Screen-Shot-2015-05-11-at-10.23.25-am.png”][et_pb_fullwidth_header admin_label=”Fullwidth Header” title=”LATEST NEWS” background_layout=”dark” text_orientation=”left” /][/et_pb_section][et_pb_section fullwidth=”off” specialty=”off”][et_pb_row][et_pb_column type=”1_4″][et_pb_sidebar admin_label=”Sidebar” orientation=”left” area=”et_pb_widget_area_1″ background_layout=”light” /][/et_pb_column][et_pb_column type=”3_4″][et_pb_text admin_label=”Text” background_layout=”light” text_orientation=”left”]

NRW SECURES CONTRACT AT YANDICOOGINA MINE FOR RIO TINTO
16/10/2012

The scope of the Yandi Sustaining Project (YSP) is to expand the mine production capacity. The works will include:

• Over 1 million cubic metres of excavation for diversion drains (including 640,000 cubic metres of rock excavation)

• Over 500,000 cubic metres of embankment construction

• Over 200,000 cubic metres of levee construction

• Over 4,400 lineal metres of culverts

• Construction of a 48 metre long wide bridge over an operating railway

• Construction of 2 floodways

The Bulk Earthworks Contract is expected to run for 40 weeks commencing in late November 2012. At its peak, there will be over 300 workers required for this project.