CLIENT
Rio Tinto Iron Ore

PROJECT
Western Turner Syncline
Concrete Works

LOCATION
Tom Price, Western Australia

CONTRACT AWARD VALUE
$94 million

START DATE
May 2012

COMPLETION DATE
November 2013

PROJECT DESCRIPTION

NRW undertook the concrete and civil works at Western Turner Syncline Mine. The scope of works included the installation of approximately 21,000 cubic metres of concrete for the following areas:

  • Primary crusher
  • Overland conveyor
  • Plant utilities

The Project also included the erection of a corrugated steel arch, structural earthworks, fill around the primary crusher, fencing and bollards.

The Project ran for approximately 82 weeks and had a peak workforce of 225 personnel.