CLIENT
Rio Tinto Iron Ore

PROJECT
Pannawonica Tunnel
Bridge Repair

LOCATION
Pilbara, Western Australia

CONTRACT AWARD VALUE
$17 million

START DATE
July 2009

COMPLETION DATE
November 2009

PROJECT DESCRIPTION

This project for earthworks, rail and concrete at Bridge 11, Pannawonica required the replacement of the flood damaged bridge with two large 25 metre diameter multi plate arches.

With work requiring completion by the end of November in order to eliminate the potential for river flow, this Project was high risk for the timeframe.

The Project was completed ahead of schedule and was undertaken in Joint Venture with our Indigenous partner Ngarluma and Yindjibarndi Foundation Limited (NYFL).