CLIENT
Rio Tinto Iron Ore
PROJECT
Pannawonica Tunnel
Bridge Repair
LOCATION
Pilbara, Western Australia
CONTRACT AWARD VALUE
$17 million
START DATE
July 2009
COMPLETION DATE
November 2009
PROJECT DESCRIPTION
This project for earthworks, rail and concrete at Bridge 11, Pannawonica required the replacement of the flood damaged bridge with two large 25 metre diameter multi plate arches.
With work requiring completion by the end of November in order to eliminate the potential for river flow, this Project was high risk for the timeframe.
The Project was completed ahead of schedule and was undertaken in Joint Venture with our Indigenous partner Ngarluma and Yindjibarndi Foundation Limited (NYFL).