KCGM Growth Project Enters Construction Phase

loading...

Big milestones for Northern Star Resources Limited at the KCGM Growth Project as the Primero team enters a major construction phase.

This Engineering, Procurement and Construction (EPC) contract for this project was awarded to our Primero business in 2023. Complete scope includes:

  • Project management
  • Engineering
  • Procurement
  • Construction
  • Commission
  • Performance testing

As of June 2025, Primero progress indicators are as follows:

Engineering: Separable Portion (SP) 1 is 90% complete, SP 2 is at 66%.

Procurement: 4 of 7 steel shipments have been delivered, with the 5th shipment sailing from China. 223 of 234 procurement packages awarded to date.

Construction: Major concrete works are well progressed and nearly 70% completed. The flotation cell pre-assembly is complete, and structural steel installation is underway!

People: 600+ people driving the project forward, with 300 on-site daily.

Well done to the Primero team for making this happen!