Previous slide
Next slide
CLIENT
Rio Tinto
PROJECT
Yandi Sustaining Project Stage 1
LOCATION
Pilbara, Western Australia
CONTRACT AWARD VALUE
$91 million
START DATE
November 2012
COMPLETION DATE
November 2013
PROJECT SUMMARY
The project consisted of bulk earthworks and bridgeworks for Rio Tinto’s Yandi Sustaining Project (YSP) to expand the mine production capacity. The works included:
- Over 2.3 million cubic metres of bulk excavation
- Over 1 million cubic metres of excavation in rock.
- 8 kilometres of heavy vehicle haul road construction
- Over 12 kilometres of sealed and unsealed Light vehicle road construction, with 4,200 metres of safety barrier
- Over 6,500 lineal metres of culverts
- Construction of a 48 metre long bridge over an operational railway
- Construction of 2 floodways
- Construction of a 23 metre high ROM wall
The contract duration was 63 weeks commencing in November 2012 with a peak workforce of 230 personnel.