CLIENT
Energy Resources of
Australia (ERA) Limited
PROJECT
Ranger Tailings Storage Facility
LOCATION
Ranger Mine, Northern Territory
CONTRACT AWARD VALUE
$10.5 million
START DATE
September 2013
COMPLETION DATE
November 2013
PROJECT DESCRIPTION
The Ranger Uranium Mine is located in the Northern Territory, 250 kilometres east of Darwin.
NRW undertook works involving capping and the construction of the tailing storage facility, which included using geo cloth laying and sheeting.
The project required 2.5 metres of capping (approximately 850,000 BCM).
At its peak there were 93 personnel involved in the works to ensure the tight schedule end dates were achieved prior to the wet season.