CLIENT
BHP Billiton Iron Ore

PROJECT
Ore Car Repair Shop

LOCATION
Pilbara, Western Australia

CONTRACT AWARD VALUE
$31 million

START DATE
August 2013

COMPLETION DATE
May 2014

PROJECT DESCRIPTION

The Ore Car Repair Shop Project comprised bulk earthworks and road construction for BHP Billiton Iron Ore’s new state of the art Ore Car Repair Shop at Mooka.

The works completed included:

  • 360,000 cubic metres of bulk earthworks
  • 70,000 cubic metres of rock excavation
  • 700 metres of drainage culvert construction
  • 7.8 km of road construction with 14mm single seal
  • 35,000m2 of Rail Maintenance Track construction including cement stabilisation and 14mm single seal

The Project ran for approximately 35 weeks and had a peak workforce of 150 personnel.